Back to education hub

6 min read

Case Study: Parking Garage EV Charging Conversion for 200+ Spaces

How a 240-unit Northern Virginia HOA wired a 280-space parking garage for EV charging using a make-ready approach and dynamic load management.

The Building and the Goal

Crestwood Plaza is a 240-unit luxury condominium in suburban Northern Virginia, built in 2008 with a four-level subterranean parking garage offering 280 deeded spaces and 30 visitor spaces. By late 2024, the HOA board was fielding two or three EV charging requests per month from residents. Six owners had already paid out of pocket for individual circuits run from their breaker panels, creating a patchwork of cabling, mismatched equipment, and complaints about who paid for what kilowatt-hour.

The board's goal was straightforward but ambitious: provide a path for any of the 280 deeded spaces to support Level 2 charging within five years, without raising assessments more than residents could absorb. They voted to pursue what their consultant called a make-ready first approach — install conduit, panels, and load management infrastructure capable of serving every space, then deploy chargers in phases as demand grew.

The board hired a turnkey installer in early 2025 after issuing an RFP to four firms. Construction ran from May through August 2025, with the first 24 chargers energized on September 12, 2025.

The Site Assessment Findings

The site assessment, performed before the RFP went out, revealed both opportunities and constraints common to mid-2000s buildings.

The good news: the original electrical service had 2,500 amps of utility capacity, of which roughly 1,400 amps was actually used at peak. That left meaningful headroom — but not enough to run 280 chargers at full 9.6 kW (40 amps) simultaneously. Without intervention, full deployment would have required a service upgrade costing around $180,000.

The constraint: the existing electrical rooms were on the parking levels but undersized. Installing the new charger panels meant building two small enclosures off-corner from the main switchgear, plus running a 1,200-foot trunk of feeder conduit along the garage ceiling. That structural work added cost but eliminated the need to upgrade utility service.

  • - Existing electrical service had 1,100 amps of available capacity at peak, after measured load.
  • - The garage had no fire suppression rated for energized EV equipment in two of the four levels — those required upgraded sprinklers per the local amendment to NFPA 13.
  • - Cellular reception in the lower two levels was poor, requiring a building-wide LTE and WiFi mesh for networked charger communication.
  • - Two existing owner-installed chargers were on circuits that did not meet NEC Article 625 requirements; they were de-energized and replaced.

Designing for 200+ Spaces Without Tripping the Building

The technical heart of the project was dynamic load management. With 1,100 amps of available capacity and a goal of supporting 280 spaces eventually, the only realistic path was to share that capacity across all active sessions through software.

The installer specified networked Level 2 chargers running OCPP 1.6 protocol, all reporting to a central management platform. The platform measures real-time draw across all chargers and modulates each session's amperage so the total never exceeds the 1,100-amp ceiling. In practice, when only ten cars are charging, each gets the full 40 amps. When fifty cars are charging, each gets roughly 8 to 11 amps — slow, but more than enough to add 30 to 50 miles of range overnight.

Future phases will add chargers in groups of 20 to 30 as demand grows. Because the conduit and panels are already in place, each future install costs roughly $1,800 to $2,400 per charger instead of the $6,000 to $9,000 typical for ground-up retrofits.

  • - Make-ready conduit, junction boxes, and panel capacity for all 280 spaces (no chargers yet, but the wiring path is complete).
  • - 24 networked Level 2 chargers physically installed and energized in Phase 1.
  • - Two new sub-panels with 800-amp and 600-amp ratings, fed from the main service.
  • - A building-wide load monitoring system tied into the chargers and the building management system.
  • - A dedicated app for residents to start sessions, see availability, and pay per kWh.

The Numbers: Costs, Incentives, and What Residents Pay

Total Phase 1 cost came in at $612,000. The largest line was make-ready electrical work — panels, feeders, and conduit for all 280 spaces — at $310,000. The 24 Level 2 chargers and their installation added $186,000. Fire suppression upgrades on two parking levels were $58,000. Communication infrastructure cost $22,000, and permitting, engineering, and project management added $36,000.

Incentives offset roughly $148,000 of that total. The federal 30C Alternative Fuel Vehicle Refueling Property Credit covered 30% of qualifying costs because Crestwood's census tract qualifies as non-urban under the IRS definition, returning approximately $98,000. Dominion Energy's Smart Charging Infrastructure Pilot rebate added $50,000 for the make-ready and load management components.

Net cost to the HOA after incentives was $464,000. The board funded $200,000 from reserves and financed the remaining $264,000 over seven years through a building-improvement loan at 6.4%, resulting in a special assessment of $19 per unit per month for 84 months.

Residents who use the chargers pay $0.22 per kWh, which covers the building's electricity cost (roughly $0.11 per kWh blended), maintenance reserve contributions, and software fees. Visitor sessions are billed at $0.34 per kWh.

Lessons Learned for Other Boards

Eight months in, the system is serving 31 active EV-driving households across the 24 deployed chargers, with sessions averaging 14 per day. Chargers are typically available within 20 minutes of request during peak evenings, and the load management software has never tripped a main breaker.

Boards facing similar decisions should confirm their local fire code requirements early, since amendments to NFPA 13 and NFPA 855 vary widely by jurisdiction and can add 10% or more to total project cost when discovered late. They should also build in time for resident communication — Crestwood's board held three town halls before the vote, including a dedicated session for non-EV-driving owners explaining why they were paying $19 a month for infrastructure they wouldn't immediately use.

  • - Make-ready first pays back fast: adding chargers in Phase 2 will cost about a quarter of what comparable buildings pay for one-off retrofits, with break-even at roughly 60 total chargers installed.
  • - Software is not optional at this scale. Without dynamic load management, the project would have required a $180,000 utility service upgrade and still could not have supported every space charging at once.
  • - Communicate the assessment clearly and early. The framing that won approval at Crestwood was future-proofing the building's resale value and avoiding the inevitable patchwork of unauthorized installations.
  • - Treat the existing owner-installed chargers as a liability to retire, not a feature to preserve — most pre-existing one-off installs do not meet current code.

Ready to Find an EV Charging Installer?

Browse our directory of verified EV charging vendors for multifamily properties and HOAs. Request quotes from top installers in your area.

Browse Vendor Directory